The referenced VDOT revenue share project consists of turn
lane improvements, signalization and some curb and gutter
installation pursuant to the approved construction plan and
profiles for this Route 605/602 intersection. It represents
one of two pending VDOT Revenue Share Projects associated
with Auburn Middle School, the Brookside Community and the
opening of Kettle Run High School and Greenville Elementary
School. All right-of-way and easements have been acquired
and recorded. Although it took longer than targeted, the
wait was worth it, since NOVEC, Comcast and Verizon
relocated all utilities at no charge to the County
The Department of Community Development has properly
advertised the project, conducted its required pre-bid
conference and received bids by its advertised January 26,
2009 deadline. The nine bids received ranged from $452,403
to $578,503; the County needs authorization to execute a
contract with SW Rodgers Company, who presented the low
responsible bid. The bids have been evaluated by a Committee
including the County Procurement Office, County Engineer and
a representative from McDonough Bolyard & Peck. VDOT is
issued the required authorization to award and proceed with
the project. Therefore, once the contract is finalized and
executed, the County can immediately provide the contractor
with the notice to proceed.
|