RESOLUTION

A Resolution to approve SEA03-L-01, AMENDING a Previously Approved Special Exception for Luck Stone Corporation to Allow Restricted Use of a Private Road for Deliveries of Construction materials to the Marsh Run Generation Corporation Peaking Facility Construction Site on old Grassdale Road Off of Lucky Hill Road

WHEREAS, the Fauquier County Board of Supervisors previously granted Special Exceptions 1212, 1590, 25690 and 27420 permitting Luck Stone Corporation to operate a quarry upon certain terms and conditions; and

WHEREAS, the terms and conditions of the special exceptions prohibited the use of a private road on the Luck Stone Corporation properties; and

WHEREAS, on November 15, 1999, the Board of Supervisors amended that condition (SE99-L-43) to permit the restricted use of the private road for delivery of concrete, stone, asphalt, turbines and other construction materials to the Virginia Power Peaking Facility located on Route 655 (Lucky Hill Road); and

WHEREAS, the amendment was approved to alleviate safety issues associated with the use of Lucky Hill Road by heavy construction and industrial traffic; and

WHEREAS, the Board of Supervisors wishes to amend this special exception condition to allow the same restricted use for the same type of materials being delivered to the construction site of the approved Marsh Run Generation Corporation (a.k.a. Old Dominion Electric Cooperative) Peaking Facility; and

WHEREAS, the Fauquier County Planning Commission has conducted a public hearing on this proposed Special Exception Amendment and has forwarded a recommendation of approval subject to certain conditions; and

WHEREAS, such an amendment will limit the amount of heavy construction and industrial traffic on Lucky Hill Road and other nearby public roads; now, therefore, be it

RESOLVED by the Fauquier County Board of Supervisors this 18th day of February 2003, That SEA-L-01, an amendment to the Special Exception Condition prohibiting the use of the private road located on the Luck Stone Corporation be, and is hereby, approved, subject to the following conditions:

  1. That the amendment be limited to allow the use of the Luck Stone private road only to permit delivery of concrete, stone, asphalt, turbines, and other construction materials and equipment directly related to the construction of the Marsh Run Generation Corporation Peaking Facility.
  2. That ODEC monitor the use of the Luck Stone private road to assure that the road is only used for traffic related to the construction of the Marsh Run facility.
  3. That the term of this amendment will be limited to the duration of the construction of the Marsh Run Peaking Facility, and will expire upon completion of that facility.