ATTACHMENT 1
From:
Owen Bludau, Vint Hill EDA
Date: April 4, 2002
The
VHEDA has been having extensive discussions with Ed Miller in attempting to
find a feasible solution to extension of the parkway.
So far, a solution has
not been found. The VHEDA
Board and its legal counsel had a long discussion yesterday of the
revised edition of the Brookside/Brookfield Farms
proffers (however, I do not believe we have the current edition) and of
a draft agreement submitted by Ed Miller to the VHEDA.
We have some continuing
issues. 1.
We notice a conflict between the revised proffers in which the applicant
states that he will construct the extension of the parkway to the traffic
circle. In the agreement he
submitted to the VHEDA, he places the full cost for everything except the
final paving of two lanes on the VHEDA. The
VHEDA Board is very concerned about the precedent that a third party (the
applicant) can attempt to change legal proffers between the VHEDA and the
Board of Supervisors that have already been approved.
And to do so without
approval of the two contract parties.
This change would be to force the
VHEDA to pay for a proffer that it had not volunteered and to expedite expenditures
for proffers that were to be based on traffic counts, sale of designated
amounts of FAR and projections of financial ability to construct the
proffers. We
are examining every way within our financial limits to see if we can make something
work on extension of the parkway on Vint Hill.
What Ed Miller and the
County need to understand is that actual cost of construction of the two lanes
of the parkway extension will require additional secondary costs by the
VHEDA. The applicant has
proffered to extend the parkway "to the traffic
circle". He does not
proffer to construct the traffic circle at Kennedy
Road. Construction of the
traffic circle will require realignment of
900 feet of Kennedy Road to achieve proper intersection angles.
It will require
relocation of existing utility lines along Kennedy Road.
The VHEDA would
have to pay that when the parkway is extended under the applicant's proffers. A
minimum of 500 feet of Aiken Drive (formerly Harrison Road) will also have to
be realigned to achieve a 90 degree intersection.
Preferably 1900 feet need
to be realigned, but could be deferred.
Existing utility lines along Aiken
Drive will also have to be relocated.
Those costs are not included in the
proffer. It
currently appears that the VHEDA will incur a minimum of $510,000 in required
secondary costs from extension of the parkway.
That would be in addition
to the projected $910,000 cost of the two lanes of the parkway extension that the applicant is attempting to pass on to the VHEDA. |