Attachment 2 PROPOSED DEVELOPMENT CONDITIONS SE
01-S-14. (OPEN SPACE REDUCTION) MAY
9, 2002 If it is the intent of the Fauquier County Board of
Supervisors to approve SE 01-S-14 for an open space reduction, the staff
recommends conformance with the following development conditions: 1.
This special exception is granted for and runs with
the land indicated in this application and is not transferable to other
land, except that parcels included in CPA 00-S-05 as set forth therein may
be used to provide the open space for Brookside as set forth in #5 below. 2.
This special exception is granted only for the
purpose(s), structure(s) and/or uses indicated on the special exception
plat dated May 9, 2002 as approved with this application, as qualified by
these conditions. 3.
In ensuring that the open space approved with this
application is provided, a density of no more than 1 dwelling unit per
gross acre shall be permitted in all phases of the Brookside/Brookside
Farm development, including previously approved phases of Brookside. 4.
Open space shall be provided in locations as
generally depicted on the special exception plat approved with this
application. 5.
The Adjacent Owners (as defined in Attachment C of
the Brookside Farm PRD Revised Rezoning
Proffers, dated April 1, 2002) shall provide open space on subject
properties in the R-1 zoning district as set forth in Article 2, Part 309
of the Fauquier County Zoning Ordinance, with the following provisions:
6.
The applicant agrees that as part of the
justification for reducing the open space in Brookside, the residents of
Brookside shall have full access to the open space areas and associated
facilities (trails, parks, active recreation areas, etc.) of Brookside
Farm PRD as an integrated community. PROPOSED DEVELOPMENT CONDITIONS SE 01-S-15
(FLOODPLAIN CROSSINGS) MAY 9, 2002 If
it is the intent of the Fauquier County Board of Supervisors to approve of
SE 01-S-15 for floodplain uses pursuant to Sect. 5-2300 of the Fauquier
County Zoning Ordinance, the staff recommends conformance with the
following development conditions: 1.
The
special exception is granted for and runs with the land indicated in this
application and is not transferable to other land, except that parcels
included in CPA #00-S-05 as set forth therein may be used to provide a
location for the floodplain uses, subject to the conditions set forth
herein. 2.
This
special exception is granted only for the purpose(s), structure(s) and/or
uses indicated on special exception plat dated May 9, 2002 as approved
with the application, as qualified by these development conditions. 3.
There
shall be no significant increase in flood levels or velocity of
floodwaters offsite as a result of this floodplain crossing, as determined
to the satisfaction of the County Engineer prior to construction plan
approval for any phase of development that includes one of the crossings. 4.
Prior
to construction plan approval for any phase of the development that
includes a crossing, the applicant shall obtain a Conditional Letter of
Map Revision (CLOMR) from the Federal Emergency Management Agency (FEMA). The applicant shall request a final Letter of Map Revision (LOMR)
within 90 days of completing construction of the floodplain crossing.
Bonding will be required to cover the amount of the LOMR fee, the
as-built plans and any other requirements as outlined in FEMA’s CLOMR. 5.
The
floodplain study submitted to FEMA for the parkway crossing shall be sized
for a four-lane divided highway. Both
crossing shall be sized to include any planned recreational trail
construction. 6.
The
Final Plat for each phase of the subdivision including a floodplain
crossing shall show the revised floodplain limits.
In no instance shall more than 25% of any individual residential
lot be covered with floodplain. 7.
The
floodplain crossing design shall be submitted to the County for approval
as part of the final construction plans for any phase of the subdivision
that requires such crossing, using acceptable engineering design. 8.
Any
land disturbed within the floodplain shall be stabilized with either
temporary or permanent seed in accordance with Virginia Erosion and
Sediment Control Regulations. 9.
Prior
to the issuance of any additional land disturbing permits for a phase of
project that includes a floodplain crossing, the applicant shall submit
written evidence indicating to the County Engineer that the US Army Corps
of Engineers has approved any disturbance within wetland area. 10.
The
exact location of the floodplain crossings shall be determined with the
final construction plans for any phase of the subdivision that includes a
floodplain crossing, and may be installed at a different location provided
that the relocated crossings do not cause an increase in off-site
floodplain elevations. PROPOSED
DEVELOPMENT CONDITIONS SE 01-S-16. (PUBLIC
UTILITIES) REVISED MAY 9, 2002 If it is the
intent of the Fauquier County Board of Supervisors to approve SE 01-S-16
for public utilities uses pursuant to Sect. 5-2000 of the Fauquier County
Zoning Ordinance, the staff recommends that the Board of Supervisors’
approval be subject to the following development conditions:
|