A maximum of 90 days will be
provided for execution of the PDR Commitment Agreement after
Board of Supervisors approval. If not received, the County
has the right to rescind the offer. In addition, a period
of one year from date of execution of the Commitment
Agreement is established for landowners to show significant
progress toward completion. If there has been no progress,
the County may rescind the offer. Should additional time be
required, a written request must be made outlining progress
made and explains the reasons for the request. One
additional year may be granted; however, if the easement is
not completed within this timeframe, the County may rescind
the offer. The landowner would be required to reapply in a
subsequent application round to be considered for the PDR
Program. These timeframes will be effective starting with
the next application round, open from June 1, 2006 to August
31, 2006. |