AGENDA REQUEST

Sponsor:

Board of Supervisors Meeting Date: 

Sharon G. McCamy , Vice Chair, Lee District

June 17,2002

Staff Lead:

Department: 

Paul S. McCulla

County Attorney's Office

Topic: 

A Resolution to Approve / Deny the Request of Dominion Virginia Power to be Relieved of the Obligation Set Forth in Condition Number 3 of the Final Order of the Board Dated November  5, 2001, with Respect to Cool Lawn Farms and the Ritchie Property

Topic Description:

On March 13, 2002, Dominion Virginia Power submitted a request to be relieved from its obligation under Condition number 3 of a Final Order, adopted by the Board of Supervisors on November 5, 2001.  The Final Order related to Dominion Virginia's proposal to acquire additional right-of-way in the Southern Fauquier Agricultural and Forestal District, in order to construct a new 34.5 kv power line adjacent to an existing power line.  The Final Order provided in pertinent part: 

"Should the governing body of any other jurisdiction approving a portion of this electric line project require a less impactive method of constructing the 34.5 kv electric feeder line such construction shall also be used in this agricultural-forestal district.    Dominion Virginia Power shall have the right to apply to the Board of Supervisors to be relieved from the obligations of this condition upon a showing that the less impactive method imposed in the other jurisdiction will not result in a lessening of the impact in this jurisdiction or would be uneconomical or impractical, which decision shall be in the sole discretion of the Board of Supervisors." 

A copy of the request is attached hereto.

Requested Action of the Board of Supervisors: 

Consider the request of Dominion to be relieved of the above-referenced condition, and grant or deny the request.  Resolutions to deny or approve the request are attached hereto.

Financial Impacts Analysis:

None.

Identify any other Departments, Organizations or Individuals that would be affected by this request:

None.