A RESOLUTION TO BORROW $4,000,000 TO UPGRADE THE HVAC MECHANICAL SYSTEMS AT LIBERTY HIGH SCHOOL
WHEREAS, for several years the Fauquier County School Board has had air quality concerns, including mold, at Liberty High School; and
WHEREAS, the Fauquier County Board of Supervisors appropriated $1,061,341 in FY 2002 for air quality improvements at Liberty High School, of which $653,072 was spent on mold remediation; and
WHEREAS, the School Board has determined that the Liberty High School HVAC system continues to be inadequate to provide the necessary air quality and climate control; and
WHEREAS, the School Board contracted the firm of Setty and Associates, Ltd., to provide recommendations for mechanical systems upgrades to Liberty High School; and
WHEREAS, the School Board chose the recommended option to replace the unit ventilators with the new fan coil units having chilled water cooling coils, hot water heating coils, plus heat reclaim makeup air units, costing $4,769,996; and
WHEREAS, on March 8, 2004, the School Board adopted a resolution requesting the Board of Supervisors fund this project; and
WHEREAS, approximately $770,000 is available for this project from the residual of the initial funding for the HVAC project and from an adjustment to FY 2005 School Capital Improvements Plan projects; and
WHEREAS, $4,000,000 in unfunded (not supported by actual dollars) appropriation is in the Capital Improvements Plan projects for Warrenton and Taylor Middle Schools renovations; and
WHEREAS, due to the significant increase in estimated costs for the Taylor and Warrenton Middle School renovations, the School Division has decided not to pursue those projects at this time; and
WHEREAS, on May 20, 2004, the County Finance Committee considered this issue and recommended the transfer of $4,000,000 from the Taylor/Warrenton Middle Schools renovations projects to the Liberty High School HVAC project, and that the borrowing to support this action be taken at the earliest opportunity; and
WHEREAS, on June 21, 2004, a public hearing was held on the proposed funding to solicit comments from Fauquier County citizens on borrowing $4,000,000 to upgrade the Liberty High School HVAC mechanical systems; now, therefore, be it
RESOLVED by the Fauquier County Board of Supervisors this 21st day of June 2004, That $4,000,000 is authorized to be transferred within the Capital Improvements Plan from the Warrenton /Taylor Middle Schools renovations projects to the Liberty High School HVAC project to support the upgrade option chosen by the School Board; and, be it
RESOLVED FURTHER, That the Finance Director is to initiate the process to borrow the necessary funds in a timely manner; and, be it
RESOLVED FINALLY, That the Fauquier County Board of Supervisors Board does hereby authorize the School Board to take those actions necessary, within the funding appropriated, to complete the HVAC mechanical upgrades at the earliest opportunity.
|
|||||||||||||||||||||||||||||