CONSENT AGENDA REQUEST
|
Owners/Applicants:
|
Board of Supervisors Meeting Date:
|
Prospect Development Company,
Inc.
|
June 24, 2004 |
Staff Lead:
|
Department:
|
|
Charles A. Floyd, Senior Planner |
Community Development
|
|
Magisterial District:
|
PIN: |
|
Cedar Run |
7940-79-2131-000 |
Topic:
|
Consider
Preliminary Plat Subdivision Application PPLT04-CR-004:
Heddings Springs Estates
|
|
Topic
Description:
|
|
The applicant is seeking Preliminary Plat approval to divide
approximately 107.10 acres into five (5) single-family
residential lots ranging in size from
±1.70 to 4.58
acres, with a residue parcel of
±92.08 acres. The
±92.08 acres, or
residue, will need to be placed in a non-common open space
easement with the Final Plat, because it will have no
further subdivision potential. The applicant is also
requesting a waiver of the maximum cul-de-sac length of 700
feet as outlined in Section 5-8 of the Subdivision
Ordinance. The proposed cul-de-sac length is
±2000 feet from its
intersection with Heddings Road.
The property is
situated on the west side on Heddings Road (Route 794) at its
terminus. The property is located in both Fauquier and Prince
William County. The entire subject property is approximately
133.58 acres, of which ±26.48
acres are located within Prince William County, leaving the
balance of ±107.10
acres subject to Preliminary Plat review in Fauquier County.
Within the County, the subject property is zoned Rural
Agricultural (RA). All adjacent properties are also zoned Rural
Agricultural (RA).
In accordance
with the State Code requirements for adjacent jurisdiction
notification, Prince William County has reviewed the Heddings
Springs Estates Preliminary Plat. They have noted the portion
of the property that falls within Prince William County,
approximately 26.5 acres, is shown on the plans within the
100-year FEMA floodplain and is not proposed at this time to be
developed. The proposed subdivision of minimum 40,000 square
foot lots in the Fauquier County portion of the property will
setback from the Prince William County line and will be buffered
from the Rural Area in Prince William County by a 92.08-acre
parcel and a 100-year floodplain conservation easement. Prince
William County finds these aspects of the plan acceptable.
Section 9-7 of
the Subdivision Ordinance requires that "…all preliminary plats
approved by the Planning Commission shall be referred to the
Board of Supervisors at its next regularly scheduled meeting…If
the Board takes no action on the preliminary plat referral, the
preliminary plat shall be deemed approved in accordance with the
actions of the Planning
Commission."
The Planning Commission staff reports are
available upon request.
|
|
Requested Action of the Board of Supervisors: |
|
No action is necessary, unless a majority of the Board
wishes to consider this preliminary subdivision
application. On May 27, 2004, the Planning Commission voted
to approve the Heddings Springs Estates Preliminary Plat,
subject to the conditions noted below:
- The
Final Plat shall be in general conformance with the
Preliminary Plat entitled "Heddings Springs Estates"
dated August 20, 2003, signed by Theodore D. Britt
4-01-04 and received in the Planning Office on April 1,
2004, except as modified by these conditions. This
approval is for a maximum of five (5) residential lots,
and a non-common open space parcel.
- Out
parcel one (1) shall be boundary line adjusted into
parcel PIN 7940-66-2345-000, prior to Final Plat
approval.
-
SWM/BMP’s shall be required. Conservation easements
alone will not satisfy the BMP criteria. Final
Construction Plans shall meet the minimum criteria of
the Fauquier County SWM Ordinance.
- Road
culverts shall be sized so as not to back water on the
upstream property during a 10-year storm. The applicant
shall be required to obtain offsite drainage easements
if the 10-year storm drainage is backed onto adjacent
properties.
-
Several soils identified on the soils map are hydric or
have hydric inclusions. Wetlands may exist. Any wetlands
shall be identified and applicable permits shall
obtained prior to submission of the Final Construction
Plans and necessary permits shall be submitted with the
first submission of the Final Construction Plans.
- VDOT
may require a special road design for the portion of the
road that crosses high shrink swell and/or low capacity
soils.
- A
Virginia Certified Professional Soil Scientist (CPSS)
shall adjust the Type I Soil Map soil lines or shall
adjust the preliminary soil map with revisions onto the
final construction plan. This shall be done in the field
and checked for any additional soils information to be
added to the final construction plan.
-
Interpretive information from the Type I soil report for
each mapping unit shown on the above final construction
plan shall be placed on the same sheet as the soil map.
Also, a Symbols Legend shall be placed on the final
construction plan to identify spot symbols.
- This
final soil map shall be filed in the front office of
Community Development and the Building Department to be
used exclusively for obtaining soils information for
this proposed subdivision.
- Two
copies of this final soil map with original CPSS
signature shall be submitted to the Soil Scientist
Office before final plat approval is made.
- Per
VDOT’s March 18, 2004 comments, drainage easements are
needed for any portion of the drainage structure outside
of the right-of-way, and to the point where an adequate
channel is obtained. The culvert crossing shown on the
plan has been increased in size from the previous plan,
and there does not appear to be enough area on the
proposed right-of-way or the outparcel to provide a
drainage easement sufficient to accommodate the
structure including the riprap. It appears as if a
drainage easement will need to be obtained from the
adjacent property owner. In addition, it appears as if
guardrail is being indicated. If guardrail is required,
an additional two feet of shoulder needs to be provided.
- A
signature block shall be placed on this plat for the
CPSS to sign which states:
|
Preliminary Soils Information
Provided by the Fauquier County Soil Scientist
Office via a Type I Soil Map (1” = 400’) Dated June
19, 2003.
This Virginia Certified
Professional Soil Scientist has field reviewed and
adjusted the preliminary soil information onto the
final plat (1” = 50’) and certifies that this is the
Best Available Soils Information to Date for Lots 1
– 9.
Va. Certified Professional Soil
Scientist
DATE
CPSS #3401-___________ |
- These
statements under Home Sites and Road Construction
shall be placed on the same sheet as the final
soils map:
·
The County recommends that no below grade
basements be constructed on soil mapping units 14A, 14B,
62B, 78A, 79A, 173A, 173B and 178A due to wetness unless the
foundation drainage system of the structure is designed by a
Virginia Licensed Professional Engineer. The foundation
drain lines should be day lighted for gravity flow on all
structures.
·
Prior to final construction plan approval it
shall be agreed that all drainfield areas are to be
surrounded by safety fencing and no construction traffic
shall cross nor shall land disturbance occur in these areas.
The fencing of these areas is to be verified by county staff
before the issuance of the land disturbing permit.
Financial
Impacts Analysis:
None. |
Attachment:
1.
Preliminary Plat
|