RESOLUTION


 

A RESOLUTION TO APPROVE A CONTRACT WITH MILLER BROTHERS, INC. TO CONSTRUCT AN ADDITION TO THE MARSHALL COMMUNITY CENTER

 

WHEREAS, the Fauquier County Board of Supervisors has appropriated funding for an addition to the Marshall Community Center; and

 

WHEREAS, through reallocation of funds additional funding has been made possible to provide for the construction contract as well as construction administration, contingencies and other costs associated with the project; and

 

WHEREAS, Miller Brothers, Inc. has submitted the low bid of $444,850 for the project; and

 

WHEREAS, the Parks and Recreation Board and the Facilities Planning and Implementation Committee have identified changes that reduce the cost to $434,850; now, therefore, be it

 

RESOLVED by the Fauquier County Board of Supervisors this 21st day of June 2004, That a contract with Miller Brothers, Inc. in the amount of $434,850 for construction of an addition to the Marshall Community Center be, and is hereby, approved.