CONSENT AGENDA REQUEST Owner/Applicant: Board of Supervisors Meeting Date: J & R Land Investments July 13, 2006 Staff Lead: Department: Holly Meade, Senior Planner Community Development Magisterial District: Center PIN: Service District: Warrenton 6994-27-7561-000, 6994-26-8780-000 6994-37-4250-000, 6994-36-7932-000 Topic: Cedar Mill Subdivision: Preliminary Plat PPLT06-CT-018, Center Magisterial District Topic Description: The applicant is seeking Preliminary Plat approval to divide approximately 79.5180 acres into forty-three (43) single-family residential lots, all containing a minimum of 40,000 square feet. As proposed, water will be provided by Fauquier County Water and Sanitation Authority and sewage will be provided with individual on-site sewage disposal systems. A copy of the Preliminary Plat is included as Attachment 1.The current Preliminary Plan includes an additional property known as the adjoining “Clyde Property”. The major issue associated with the previous development was the public water requirement. That issue was addressed in a December 8, 2005 Board of Supervisors resolution for a Comprehensive Compliance Review (CCRV06-CT-001), allowing a developer to connect to public water provided conditions of a Developer Agreement are met. A copy of that agreement is included as Attachment 2. Since that time the applicant has been working with staff and VDOT to determine a scope of work and road sections associated with the improvements on Atlee Road and Frytown Road required by said Developers Agreement. The applicant feels they have presented the preliminary scope and road section agreed to by the client and VDOT in the plan set provided. Location: The properties are located at the intersection of Atlee Road and Frytown Road (Route 674) and Academy Hill Road (Route 678), between the Woods of Warrenton and Whisperwood Subdivisions.
Adjacent Zoning/Land Use: All adjacent properties to the North, South, East and West are zoned Residential-1 (R-1). Requested Action of the Board of Supervisors: No action is necessary, unless a majority of the Board wishes to consider this preliminary subdivision application. On May 25, 2006, the Planning Commission voted unanimously to approve the Cedar Mill, subject to the following conditions:
The cross sectional area of the natural drainage corridor features that should be protected (excluding driveway/culvert crossing) shall be defined as that which is defined by the post-developed 10-year runoff discharge to be conveyed within it. An improved drainage corridor in its existing location, cleared of debris/obstructions and protected against erosion, may be considered. This shall be achieved where possible as determined by the Director of Community Development.
a. A Virginia Certified Professional Soil Scientist (CPSS) needs to adjust the preliminary soil map onto the final construction plan. This needs to be done in the field and checked for any additional soils information to be added to the Final Construction Plan. b. A signature block shall be placed on this plat for the CPSS to sign which states: Preliminary Soils Information Provided by a Type I Soils Report (1” = 400’) Dated December 17, 2001. This Virginia Certified Professional Soil Scientist has field reviewed and adjusted the preliminary soil information onto the final plat (1"=___') and certifies that this is the Best Available Soils Information to Date for Lots 1-____.
Va. Certified Professional Soil Scientist DATE CPSS #3401- c. Interpretive information from the Type I soil report for each mapping unit shown on the above Final Construction Plan shall be placed on the same sheet as the soil map. Also a Symbols Legend shall be placed on the Final Construction Plan to identify spot symbols. d. This final soil map will be filed in the Building Department to be used exclusively for obtaining soils information for this proposed subdivision. e. Two copies of this final soil map with CPSS signature need to be submitted to the Soil Scientist Office before final plat approval is made. f. The final signature sets will require original CPSS signature. g. The following statements shall be placed on the same sheet as the final soils map: i. Due to landscape position (drainageways) and high seasonal water tables the following statement needs to be placed on the final construction plan to be placed in the front office of Community Development: "The County recommends that no below grade basements be constructed on soil mapping units 4A, 15B, 16B, 17B, 17C, 48A, 93B415B, and 416B due to wetness unless the foundation drainage system of the structure is designed by a Virginia Licensed Professional Engineer. The foundation drainlines should be daylighted for gravity flow on all structures." ii. Roads built on 4A, 16B, 17B, 17C, and 93B will need to be designed to overcome low bearing capacity when wet. iii. The following statement needs to be placed on the final construction plan: “Foundations placed in soil mapping units that show a moderate, high, or very high shrink-swell potential in the most recent Interpretive Guide to the Soils of Fauquier County, Virginia will require a geotechnical evaluation in order to determine proper design.” iv. Soil mapping units 33C, 33D, 33E, 40B, 47D, 140B, 140D, 240B and 240D are usually shallow to bedrock. The following statement needs to be placed on the final construction plan: “The County recommends that before road or home construction begins in soil mapping units 33C, 33D, 33E, 40B, 47D, 140B, 140D, 240B and 240D, a site specific evaluation be conducted so that shallow to bedrock areas are identified. These areas generally are rippable if deep cuts or excavation is done.” v. Areas of steep slopes should be avoided due to high erosion hazard. Proper erosion and sedimentation practices need to be installed before construction begins. Soil mapping units 33D&E should be left in their natural state. Attachments: |