The
proposed fee schedule represents a comprehensive review,
update and major revision since 2003. It includes the
entire fee schedule associated with the Building Office’s
permitting and inspection activities, as well as all
categories associated with site plans, special exceptions,
text amendments to the Zoning Ordinance, zoning appeals, and
variances; special exception and rezoning applications;
preliminary and final subdivision plats, construction plans;
Agricultural & Forestal Districts; streets; and associated
technical review fees and permits.
|
|
The Board of
Supervisors conducted its public hearing on the proposed Fee
Schedules on June 8, 2006. Due to Board policy, approval of
proposed fees must be deferred for action until the July 13,
2006 meeting.
The summary
report presents the proposed Department of Community
Development Fee Schedule elements for the: (a) Building
Office (Attachment 1) and the (b) Zoning, Planning and
Technical Divisions (Attachment 2).
1.
Building Office Fee Schedule. Attachment 1 is
organized into nine categories: new construction,
electrical, plumbing, mechanical, alterations and repairs,
miscellaneous, plans review, administrative and amusement
devices. Here the existing and proposed fees for all
category items are presented. The minimum base fees for
almost all items have increased modestly, plus the following
examples have been added to the fee schedule: Occupancy
Permits – Existing Buildings, Hood Suppression System,
Emergency Off-Hour Inspection, Plan Review – Residential,
Modifications, and appeals.
2.
Zoning, Planning & Technical Fee Schedule.
Attachment 2 presents the proposed fee schedule and also has
nine basic categories: Zoning associated actions and
permits, Special Exceptions, Comprehensive Plan, Rezoning,
Site Plans, Subdivisions, Agricultural & Forestal Districts,
Streets, and Technical Review Fees & Permits. Detailed
analysis is available in the June 8th staff
report for the fee schedule public hearing. The following
table provides a comparative analysis for some of the key
fee changes included in last month’s staff report.
|
Plan
|
2006 (Existing) |
Proposed |
|
Major Site Plan:
Residential
3rd
or subsequent submissions (signature set excluded) |
$2,600 plus $100/unit, plus $10 per address unit
No fee
|
$5,000
plus $250/unit, plus $20/address unit
$750
flat fee |
|
Major Site Plan:
Non-Residential
3rd
or subsequent submissions (signature set excluded) |
$2,600 plus $100/acre, plus $10 per address unit
No fee
|
$5,000
plus $400/disturbed acre, plus $20/address unit
$750
flat fee |
|
Major Site Plan:
Telecommunications
a.
In conjunction with a special exception;
b.
Without a special exception |
$2,500
$4,500 |
$3,000
$5,000 |
|
Construction Plans:
a.
Residential
3rd or subsequent
submissions (signature set excluded)
b.
Non-Residential
3rd or subsequent
submissions (signature set excluded) |
Residential or PRD: $425, plus $0/lot
No fee
$425,
plus $70/lot
No fee |
$5,000
plus $250/lot
$600
flat fee
$5,000
plus $400/acre
$600
flat fee |
|