Financial Impacts Analysis:
The Registrar’s
Office has estimated the cost of a special election to be
$22,100.
A contract for the
design of the new high school was executed in June 2004 with
Moseley Architects. The design work through 35% completion is
$735,752. The completed design costs are $1,491,390.
The preliminary
total estimated cost of a new high school expressed in 2005
dollars is $46,269,093, based on a March 12, 2004 report from
McDonough Bolyard Peck Construction Engineering. Debt service
for the balance of the project costs would be incurred beginning
in Fiscal Year 2007.
|