|
TECHNICAL
MEMORANDUM TO:
Robert C. Counts, Assistant Chief of Planning
Deirdre B. Clark, Senior Planner FROM:
Christer P. Carshult, P.E., DATE:
SUBJECT:
Toll Brothers, Inc., Warrenton Chase Warrenton
Service District SE03-C-20,
SE03-C-21, SE03-C-22, and PP03-C-17 A
technical review of the above referenced special exception requests and
preliminary plan has been performed. Revised
information addressing the review performed for the February Planning
Commission meeting was received on SPECIAL
EXCEPTIONS: Water
Storage Facility 1.
Water
supply to the proposed storage facility should be investigated to
determine the feasibility of the proposed water distribution approach.
The current proposal requires that a new waterline be extended
along 2.
No
further technical comments at this time on the proposed storage tank
itself. 3.
A
water model will be required at final design to demonstrate adequate
domestic supply as well as fire protection with the proposed system.
The model should be designed to introduce looping and redundancy in
the system. Private
Sewage Facility It is the opinion of the engineering department that
this development should occur on public sewer service, however, the
following comments are provided. 1.
The
location and extents of the mass drainfield must be identified on the
plan. It appears as though it
will be adjacent to the existing 100-year floodplain.
Drainfields should be contiguous and connected.
Primary and Reserve areas should be clearly identified. 2.
A
draft ordinance addressing these types of facilities was received in early
April of this year. It does
not appear as though the proposed sewage facility, drainfield(s), and
preliminary plan cannot meet the requirements of the WSA draft ordinance
as currently designed. (Open
Space requirements, reserve fields, performance standards with respect to
design specifications, etc.) 3.
Detailed
soils analysis will be required to determine feasibility.
A considerable portion of the site is characterized by soils that
are classified as marginal to not suited for development utilizing
conventional septic tank and drainfield sewerage.
It appears as though a significant area that will be used for the
mass drainfield adjoins an existing FEMA floodplain and will ultimately
propose drainfields adjacent to it. An
approved drainfield plat should be required prior to preliminary plat
approval. Floodplain
Uses 1.
The
FEMA regulatory floodplain must be reflected on the preliminary plan.
The floodplain represented is one that has not been submitted to
and revised by FEMA. Until a
floodplain revision has been received and processed by FEMA, the review of
this request must be based on the existing regulatory maps on file with 2.
All
applicable Federal, State, and Local (i.e. – USACOE, DEQ, VMRC, etc.)
permit requirements will need to be met prior to final approval of the
construction plans. 3.
The
plan reflects one SWM Facility and only two crossings of the 100-year
floodplain. The statement of
justification references “several lines” necessary to cross the
floodplain. All crossings must
be identified to allow for full consideration of the proposed impacts. 4.
The
SE request was to be revised to allow for potential impacts along 5.
The
revised SWM Concept Plan indicates that SWM/BMP requirements of the
development are capable of being achieved outside of what is being
represented as the “revised” floodplain limits.
All SWM/BMP facilities should be designed outside of the FEMA
defined floodplain limits. 6.
Preliminary
BMP calculations indicate that open space credit is being claimed in the
proposed drainfield locations. This
is not permitted and will need to be revised when final calculations are
prepared. PRELIMINARY
PLAN All
comments from the special exception request apply to this portion of the
review also. 1.
The conceptual layout and final design should honor the natural terrain
of the site with respect to the roadway network and future house sites.
Many of the proposed lots have slopes approaching 25% in the
location of the ultimate house pad. The
following lots may need to be revisited at the final construction plan
stage to meet ordinance requirements:
Lots 102 and 103 and others that are not as severe.) 2.
The conceptual layout and final design should honor natural drainage and
water features such as existing wetlands, drainage swales, and springs.
Many of the proposed lots have these features across them in the
location of the ultimate house pad. The
following lots may need to be revisited at the final construction plan
stage to meet ordinance requirements:
Lots 20, 27, 34, 38, 57, 65, 66, 67, 69, 70, 73, 74, 75, 76, 77,
128, 135, 140, 143, 144, 147, and others that are not as severe.) 3.
A detailed overlot grading plan will be required at final construction
plan preparation. 4.
The identified wetlands will need to be verified by the US Army Corps of
Engineers (COE). Any impacts
will need to be approved and permitted by the COE prior to final
construction plan approval. 5.
At all existing Inter-parcel connections, the applicant will be required
to perform all final construction and remedial work offsite within the
provided temporary construction easements to make the final connection
functional and permanent. 6.
A detail of the transition from the proposed curb and gutter street
section to existing ditch section will be required at all Inter-parcel
connections. 7.
Sidewalks must be 5’ in width or other It
is recommended that written correspondence be obtained addressing the
above items prior to recommendation for approval of the preliminary plat. Please
note that additional technical issues may arise at the final design stages
that are not readily apparent with this submittal. Should you have any questions regarding this review,
please contact me. |