PUBLIC HEARING AGENDA
REQUEST |
|
Sponsor: |
Board of Supervisors
Meeting Date: |
|
Raymond E. Graham, Chairman,
Cedar Run District Supervisor |
August 11, 2005 |
|
Staff Lead: |
Department:
|
|
Bryan Tippie, Director |
Budget Office |
|
Topic: |
|
A Resolution to Amend the FY
2006 Adopted Budget to Provide an Additional $2,100,000 for
Upgrading the Heating, Ventilation and Air Conditioning
(HVAC) Mechanical Systems of Liberty High School |
|
Topic Description: |
|
In June 2004, the Board of
Supervisors approved $4,000,000 in funding for the Liberty
High School HVAC project to improve air quality at that
facility. Previously, $4,769,996 has been appropriated for
this project. Earlier this month, bids were opened for
upgrading the HVAC system and they reflected the recent
escalating costs of all types of construction and
renovation. To fund the HVAC alternative upgrade plan
initially requested by the School Division will now require
an additional $2,100,000. The total cost of the project
would be $6,869,996.
|
|
Requested Action of the
Board of Supervisors:
|
|
Consider adoption of the attached
resolution. |
|
Financial Impacts Analysis: |
|
If
borrowed, the debt would impact beginning in FY 2007 and be
approximately $210,000 annually for 20 years. |
|
Identify any other
Departments, Organizations or Individuals that would be
affected by this request: |
|
Budget
Office
Finance
Department
School
Division
Attachment:
Memo from the Finance Director |
|