RESOLUTION A
RESOLUTION TO RECOMMEND DENIAL OF SPECIAL EXCEPTION # SE02-L-30 JAMES
R. AND BETTY L. MILLS, PROPERTY OWNERS COMMUNITY
WIRELESS STRUCTURES, APPLICANT PARCEL
IDENTIFICATION NUMBER 6888-38-9459-000
WHEREAS, James R. and Betty L. Mills, owners, and Community
Wireless Structures, applicant, have filed an application to
construct a 150-foot telecommunications tower under the provisions of
Articles 5-2000 and 11-102 of the Fauquier County Zoning Ordinance; and
WHEREAS, the Planning Commission held a public hearing on this
application on June 27, 2002 and has made a recommendation of denial to
the Board of Supervisors; and WHEREAS,
the Board of Supervisors has considered the written and orally presented
information of the applicants and conducted a public hearing on this
application; and WHEREAS,
the Board of Supervisors has determined that the applicant has failed to
demonstrate that telecommunications services could not be provided at a
height lower than the requested 150 feet; and WHEREAS,
the Board of Supervisors has determined that the owner has other
reasonable uses of the property; now, therefore, be it RESOLVED
by the Fauquier County Board of Supervisors this 19th day of
August 2002, That the application by Community Wireless Structures to
construct a 150-foot telecommunications tower on the property of James R.
and Betty L. Mills is not in substantial accordance with the Fauquier
County Comprehensive Plan; and, be it RESOLVED
FURTHER, That Special Exception Application #SE02-L-30 be, and is hereby,
denied as it does not satisfy the standards for approval of a special
exception application as outlined in Section 5-006, the additional
standards for Public Utilities uses in Section 5-2002 nor the provisions
in Article 11 of the Fauquier County Zoning Ordinance. |