ORDINANCE
AN
ORDINANCE AMENDING SECTIONS 4-16, 7-10, 8-2, 9-5, AND 10-5 OF THE FAUQUIER
COUNTY SUBDIVISION ORDINANCE AS THEY RELATE TO THE
STORMWATER
MANAGEMENT ORDINANCE
WHEREAS,
the Fauquier County Subdivision Ordinance Section 4-16 Bonding
Requirements, Section 7-10 Grades, Section 8-2 Ditch Cross Section,
Section 9-5 Preliminary Plan Requirements, and Section 10-5 Additional
Subdivision Requirements provide for the design criteria, review, and
bonding requirements for stormwater management in subdivision
applications; and WHEREAS,
the Board of Supervisors is concerned that applicants appropriately manage
stormwater generated by a proposed subdivision, and that off-site impacts
of stormwater generated by new development be minimized; and WHEREAS,
the Fauquier County Planning Commission held a public hearing on these
proposed Subdivision Ordinance text amendments on June 25, 2002 and voted
to recommend that the Subdivision Ordinance be amended; and WHEREAS,
the Board of Supervisors held a public hearing on this proposed
Subdivision Ordinance text amendment on August 19, 2002 and received
citizen comment on the proposed amendment; and WHEREAS,
the Board of Supervisors wishes to consider amendments to these sections; now,
therefore, be it ORDAINED
by the Fauquier County Board of Supervisors this 19th day of
August 2002, That Sections 4-16,7-10, 8-2, 9-5, and 10-5 of the Fauquier
County Subdivision Ordinance be, and are hereby, amended to read as
follows: SECTION 4 - PLAT PREPARATION
PROCEDURES, GENERAL 4-16 Bonding
Requirements Prior
to acceptance of (1) certify to the agent for the governing
body that the construction is complete and the costs have been paid to the
person constructing such facilities; or (2) furnish to the agent for
the governing body a certified check or cash escrow in the amount of the
estimated costs of construction or a personal, corporate or property bond,
with surety satisfactory to the governing body, in the amount sufficient
for and conditioned upon the construction of such facilities, or a contact
for the construction of such facilities and the contractors bond, with
like surety, in like amount and so conditioned; or (3) furnish to the agent for
the governing body as to the bank or saving and loan association, the
amount and the form. The
amount of such certified check, cash escrow, bond or letter of credit
shall include the total of the estimated cost of construction based on
unit prices for new public or private sector construction in the locality
and a reasonable allowance for estimated administrative costs, inflation,
and potential damage to existing roads or utilities. SECTION 7 - MINIMUM STREET
IMPROVEMENTS REQUIRED 7-10 Grades The
grades of streets submitted on subdivision plats shall be approved by the
Virginia Highway Department Engineer prior to final action by the agent
for the Fauquier County Board of Supervisors and shall be in accordance
with the road designs and standards of the County of Fauquier.
SECTION 8 - SPECIAL AREA
REQUIREMENTS FOR USE OF STREET STANDARDS
8-2 Ditch Cross Section All
public streets, accessways, or service drives in subdivisions having lots
containing from 20,000 square feet to 5 acres shall be graded and paved in
accordance with the typical section that is currently provided in the
Fauquier County construction specifications and standards for the various
classifications of streets as designated.
The standards are shown as Type 1-B, 2-B, 3-B, 4-A and 4-B.
Where curb and gutter is used in lieu of roadside ditches, roadways
shall be constructed to standard typical sections for curb and gutter
streets. SECTION 9 - PRELIMINARY PLATS 9-5 Preliminary
Plan Requirements 16) Preliminary plans indicating the provision/layout for all utilities,
including but not limited to, water supply, sewage disposal, BMP's, and
stormwater management facilities as outlined in the Fauquier County
Stormwater Management Ordinance. 28) Location of any existing or proposed bridges.
Location of any proposed major culverts, SWM and BMP facilities
as outlined in the Fauquier County Stormwater Management Ordinance. SECTION 10 - FINAL PLATS 10-5 Additional
Submission Requirements B) Final Construction Plans
for subdivisions, resubdivisions or revisions, including the following
minimum information as part of the final plans: 9) Storm drainage system plans including stormwater management as
outlined in the Fauquier County Stormwater Management Ordinance.
Plans should be sufficient to build structure and outfall.
Drainage divides and summary should be shown on the plans. C) Calculations for drainage, stormwater management, BMP's, waterline flows, sewerage flows, or other areas where necessary for agency review of engineering methods, sealed and signed by a Virginia Licensed Professional Engineer or surveyor (with a 3-B license). These calculations may be included on pages of the construction plans. Stormwater Management plans shall be prepared in accordance with the Fauquier County Stormwater Management Ordinance.
PROPOSED
SUBDIVISION ORDINANCE TEXT AMENDMENTS RELATED TO STORMWATER MANAGEMENT
ORDINANCE SECTION 4 -
PLAT PREPARATION PROCEDURES, GENERAL 4-16
Bonding Requirements Prior
to acceptance of (1) certify to
the agent for the governing body that the construction is complete and the
costs have been paid to the person constructing such facilities; (2) furnish to
the agent for the governing body a certified check or cash escrow in the
amount of the estimated costs of construction or a personal, corporate or
property bond, with surety satisfactory to the governing body, in the
amount sufficient for and conditioned upon the construction of such
facilities, or a contact for the construction of such facilities and the
contractors bond, with like surety, in like amount and so conditioned; or (3) furnish to
the agent for the governing body as to the bank or saving and loan
association, the amount and the form.
The
amount of such certified check, cash escrow, bond or letter of credit
shall include the total of the estimated cost of construction based on
unit prices for new public or private sector construction in the locality
and a reasonable allowance for estimated administrative costs, inflation,
and potential damage to existing roads or utilities. SECTION 7 - MINIMUM STREET IMPROVEMENTS REQUIRED 7-10
Grades The
grades of streets submitted on subdivision plats shall be approved by the
Virginia Highway Department Engineer prior to final action by the agent
for the Fauquier County Board of Supervisors and shall be in accordance
with the road designs and standards of the County of Fauquier.
SECTION 8 - SPECIAL AREA REQUIREMENTS FOR USE OF STREET STANDARDS
8-2
Ditch Cross Section All
public streets, accessways, or service drives in subdivisions having lots
containing from 20,000 square feet to 5 acres shall be graded and paved in
accordance with the typical section that is currently provided in the
Fauquier County construction specifications and standards for the various
classifications of streets as designated.
The standards are shown as Type 1-B, 2-B, 3-B, 4-A and 4-B.
Where curb and gutter is used in lieu of roadside ditches, roadways
shall be constructed to standard typical sections for curb and gutter
streets. SECTION 9 - PRELIMINARY PLATS 9-5
Preliminary Plan Requirements 16)
Preliminary plans indicating the provision/layout for all
utilities, including but not limited to, water supply, sewage disposal,
BMP's, and stormwater management facilities as outlined in the Fauquier
County Stormwater Management Ordinance. 28)
Location of any existing or proposed bridges.
Location of any proposed major culverts, SWM and BMP facilities
as outlined in the Fauquier County Stormwater Management Ordinance. SECTION 10 - FINAL PLATS 10-5
Additional Submission Requirements B)
Final Construction Plans for subdivisions, resubdivisions or
revisions, including the following minimum information as part of the
final plans: 9)
Storm drainage system plans including stormwater management as
outlined in the Fauquier County Stormwater Management Ordinance.
Plans should be sufficient to build structure and outfall.
Drainage divides and summary should be shown on the plans. C)
Calculations for drainage, stormwater management, BMP's, waterline
flows, sewerage flows, or other areas where necessary for agency review of
engineering methods, sealed and signed by a Virginia Licensed Professional
Engineer or surveyor (with a 3-B license).
These calculations may be included on pages of the construction
plans. Stormwater
Management plans shall be prepared in accordance with the Fauquier County
Stormwater Management Ordinance. |