Fauquier County has received bids
for the final phase of the Airport runway expansion and
improvement plan. It is recommended that a contract be
awarded to the lowest bidder, General Excavation, Inc. in
the amount of $1,431,138.00. Federal and State funds will
provide 98% of the costs associated with this contract.
Additionally, Fauquier County has a
contract with Campbell & Paris Engineers for engineering and
design services at the Warrenton-Fauquier Airport.
Amendment of that contract is necessary so that Campbell &
Paris Engineers may provide engineering services related to
the Phase Three Runway Expansion and Improvement Project.
Federal and State funds also provide 98% of the costs
associated with the contract amendment.
The plan is to complete the new
runway, weather permitting, by the end of this calendar
year.
|