RESOLUTION

A RESOLUTION TO APPROVE FUNDS TO IMPLEMENT A HYDROGEOLOGICAL STUDY FOR THE OPAL SERVICE DISTRICT AND TO PROVIDE WATER SERVICE TO THE COMMUNITY OF FRYTOWN

WHEREAS, the Fauquier County Board of Supervisors requested that the Fauquier County Water and Sanitation Authority (WSA) develop a draft Implementation Plan for a public water system to serve the Opal Service District, as recommended by the Economic Development Advisory Council, Utilities Task Force; and

WHEREAS, the Board of Supervisors / Water and Sanitation Authority Liaison Committee recommended that the Implementation Plan be forwarded to the Board of Supervisors for consideration of approving the initial phase of the Plan by funding a hydrogeological study of the Opal Service District; and

WHEREAS, the Board of Supervisors recognizes the need to conclude the Frytown water monitoring, bottled water and carbon filter program by providing funds to connect the remaining six residences to a water line to be constructed under proffer by Toll Brothers, Inc.; now, therefore be it

RESOLVED by the Fauquier County Board of Supervisors this 15th day of September 2003, That $200,000 be, and is hereby, appropriated from the Fauquier County Utility Fund to fund a hydrogeological study for the Opal Service District to be repaid to Fauquier County per a proposed Water Construction Funding Agreement with the Water and Sanitation Authority (WSA); and, be it

RESOLVED FURTHER, That the Fauquier County Board of Supervisors reserves $39,000 from the Fauquier County Utility Fund Frytown account ($2,500 from Utility Fund Contingency) to complete the Frytown Water Project by funding the connection of designated contaminated wells that are under the management of the Department of Emergency Services to a main water line to be constructed under a proffer agreement with Toll Brothers, Inc.  Funds to be transferred as follows:

 

 

 

FROM

 

 

 

 

 

TO

 

 

 

Source

 

Code

 

Amount

 

Department

 

Code

 

Amount

 

 

 

 

 

 

 

 

 

 

 

 

Utility Fund Catlett/Calverton Sewer Project

 

 

4-310-044310-8215

 

$200,000

 

Opal Water Project

 

4-310-TBD

 

 

$200,000

 

Utility Fund Contingency

 

4-310-99999-9999

 

$2,500

 

Frytown Water Project

 

4-310-44910-8215

 

$2,500