|
ATTACHMENT 1
COUNTY
OF
FAUQUIER
10
Hotel Street
Warrenton, Virginia 20186
From: Ron Mabry
Re: Northern Park – Project Cost
Factors
Date: October 24, 2006
CC:
This memo provides a summary of
factors that have caused additional costs to the Northern Park project
and also notes steps that have been taken to reduce additional costs to
the project.
Additional Cost Factors
-
The first factor effecting
additional costs to the project was related to topo errors built
into the design of the park. These errors were found after site
construction had begun and has resulted in additional costs incurred
by S.W. Rodgers (site contractor). There have been additional costs
incurred from the building contractor, Miller Brothers, Inc. In
order to keep the project moving, the additional costs from the 2
contractors had to be paid but will part of an after-project account
reconciliation with the engineers, PHRA. By agreement, PHRA has not
billed for any of the work they were required to do to correct these
errors but will part of the overall account reconciliation.
-
There have been additional costs
associated with design errors on the part of the engineering firm.
Again, these items had to be paid to allow for the project to
continue but will part of a separate account reconciliation at the
end of the project.
-
Unknown site and soil conditions
resulted in additional costs to the project both for the site
contractor and for our geotech firm, WDP. Some of these conditions
were resolved with credits being applied back to the project while
others could not be accommodated.
-
We have incurred additional cost
to the project due to additional requirements imposed the E&S
inspector’s site inspections. Some of these items have been related
to repairs of storm damaged E&S control measures while others seem
to be related to conditions found in the field during an inspection.
-
Additional site preparation costs
have been incurred due to the delay in Verizon and NOVEC providing
site plans to VDOT for the relocation of existing utilities along
Rt. 55.
-
Additional costs have been
incurred due to additional requirements imposed by the Department of
Health on our water tank and water system. These items were not
identified during project design and only came to light when the
Health Department was in final review of water system plans.
-
Additional engineering costs were
incurred due to WSA requirements to connect existing connector lines
to the WSA sewer line along Rt. 55. The sewer line had to be
relocated as part of Rt 55 improvements and initial discussion with
WSA indicated they did not have any offsite connectors in the area
of Rt 55 road work.
-
Additional engineering costs were
incurred for environmental testing and reporting required by the
Community Development department as part of a special exception
permit for the floodplain.
Project Scope and Design Changes
Implemented to Reduce Overall Project Costs
-
Trails within the park were
changed, rerouted and shortened to reduce overall costs.
-
Pedestrian bridges associated with
the trail system were reduced.
-
Pedestrian bridge width was
reduced.
-
Stone walls were shortened or
eliminated altogether.
-
Concrete pigmentation was
eliminated.
-
Amphitheater design was modified
and reduced.
-
Design changes to some of the
shelters and other buildings to reduce costs.
-
Areas designated for decorative
stone were replaced with rip rap.
|