OPTION 3

FIND ALTERNATIVE ACREAGE IN COUNTY

NEW LANDFILL DEVELOPMENT

 

A.        DATE OF CLOSURE OF PERMIT 575                 2015 - 2019

 

B.        FUTURE DISPOSAL METHOD                             LANDFILLING AT NEW SITE

 

C.        IMPLEMENTATION REQUIREMENTS             MAJOR PERMIT AMENDMENT

 

D.        SCHEDULE

 

ACTIVITY

06

07

08

09

10

11

12

13

14

15

16

17

18

19

20

Operation Permit 575

Existing permitted area

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Identify new site

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Part A design/wetlands

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Part A review / approval

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Part B design

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Part B review / approval

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Construction

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Operation

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

E.         CONSIDERATIONS

 

v     Maximum area of footprint

o       Probably need 300 500 acres

v     VDOT traffic study

v     Zoning

v     Wetland mitigation

v     Maximum fill height

v     Operations at facility (e.g. CDD recycling, mulch production, scrap metal, tire collection)

v     View shed and screening

v     Leachate handling

v     Storm water management

v     Gas management

v     Long term responsibilities (Closure and Post Closure Care)

v     Life expectancy needed

 

F.         LIFE EXPECTANCY

 

v     Unknown would want at least 50 100 years

 

G.        COST PER TON

 

v     Land cost (500 acres/50 years)                                                                        $  1 - $  2/ton

v     Development costs (liner, closure, infrastructure)                                               $10 - $20/ton

v     Operations (Contractor, debt service, personnel, leachate handling )                  $50 - $60/ton

v     TOTAL                                                                                                            $61 - $82/ton