TO:                  Elizabeth Cook, Chief of Planning

FROM:            Jennifer Kilanski, P.E., Consultant / County Engineer

DATE:             November 26, 2002

RE:                   Margaret Dyson

                        CPA02-L-05

                        RZ02-L-06

The Engineering Department has reviewed the above referenced plan and has the following comments:

1.      SWM / BMP’s will be required.  Any facility will be required to be in a separate lot.  If it is intended to use the existing onsite pond, a dam safety inspection will be required to be performed by someone qualified for such inspections.

Please contact me should you have any questions.