Land Disturbing Permit/VESMP Authority Permit For Projects with an Approved Site Plan/Construction Plan/Infrastructure Plan

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

After receiving the Site Plan/Construction Plan/Infrastructure Plan Approval Conditions Letter, one of the steps to be completed before the plan can be RELEASED is approval of a Land Disturbing Permit and a VESMP Authority Permit. 

Submission Requirements 

  • Must contain original signatures (If applicant is someone other than the property owner, applicant must submit proof of authority to act as an agent for the owner) 

  • Copy of Site Plan/Construction Plan Approval Conditions Letter 

  • Stormwater Pollution Prevention Plan 

  • Responsible Land Disturber (RLD) Certification 

  • Fees due per Plan Approval Conditions Letter 

  • Thumb drive containing individual PDFs of all submission materials 

Prior to Permit Issuance Requirements: 

  • DEQ Notice of Coverage Letter for Construction General Permit (VAR10) 

  • Developer’s Agreements and Performance Guarantee approved and posted 

  • Confirmation of water and/or sewer improvements being bonded with the service provider 

  • Stormwater Management Maintenance Agreement has been recorded 

  • Any Stormwater/Drainage Easement Plats have been recorded