Plans and Projects

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

PLANS

PROJECT STATUS

Project  Start/End Dates Status  Next Phase 
Central Fauquier Sports Complex - 2 restrooms, sports field lighting, utility infrastructure (Warrenton)  10/1/24-4/15/26

Phase 2 construction start 6/6/25. 

Project on schedule.
Grace Miller Safe Route to School (Bealeton) 10/1/24-4/15/26

Construction Start 6/26/25. 

Project on schedule. 
Vint Hill Village Green Master Plan 7/22/22- 4/1/23  Master Plan Complete Schematic design proposed in CIP.
Marshall Community Center Master Plan 7/2021-6/2022  Master Plan Complete  Schematic design proposed in CIP. 
Crockett Park ADA Fish Pier and Path  11/15/23 through Spring 2026 Pier installed. Pending handrail installation. Project on Schedule
Crockett Park-Decks\Boat Docks-Engineering Design  Spring 2024 through Fall 2027 3rd submission to CommDev complete. Pending 3rd submission comments.
Shared Use Path-Laurel Ridge Community College to Central Sports Complex Summer 2024 through Summer 2028 60% design phase complete. Scoping Phase complete. Initiate ROW phase, continue to 100% plans.
      Updated 4/10/26 by M. Hanson

 

 

    Free viewers are required for some of the attached documents.
    They can be downloaded by clicking on the icons below.

    Download Acrobat Reader Download Windows Media Player Download Word Viewer Download Excel Viewer Download PowerPoint Viewer