Project Status

Print
Press Enter to show all options, press Tab go to next option

Project

Start/End Dates

Status

Next Phase

View/Map

Central Fauquier Sports Complex, Warrenton
Construction 3/4/19- 8/2020
Two fields have been sodded. One parking lot left to pave. main roadway three quarters completed. Design of artificial turf underway  Add topsoil to remaining fields and sod/sprig them with bermuda grass.Install trees and shrubs. finish entrance road and parking lot.

Central Fauquier Sports Complex Utility Plan Warrenton

  Septic drain field permameter tests completed Design septic field based upon tests   
Rappahannock Station Civil War Battlefield Remington
Design 3/27/2019- 10/2019 
 Pre-application meeting held. comments given on 35% plans will be incorporated.
Work with DHR on resolving easement issue and develop plans to 60%.  
Comprehensive Plan Update November 2019-2020 Contract going to BOCS on 11/14/19 Set up kick off meeting  

Riverside Preserve Canoe and Kayak Launch Marshall

Design  VA Outdoor Foundation creating public easement documents based upon master plan for park Take easement to BOS for approval; include kayak/canoe launch and trail bridge in capital Improvement Program so staff can apply for grants.  
Northern Fauquier County Pool  Marshall Feasibility Study 2/8/2017-7/2019 Marshall Community Advisory Board is evaluating both sites and is documenting their choice Once choice is documented we will begin working on a design scope for the pool.  
Vint Hill Flooring leveling project September 4th, 2019  Flooring project is completed. play-ability has improved some. Look for the best flooring replacement product and look into grant assistance opportunities.   
Southern Fauquier Sports Complex  Remington Concept-  Concept plan completed  Level of service needs for the number of fields will be determined during Comp Plan Update.   
Mintbrook Proffer 4 rectangular fields Bealton Construction- 2018- October 2019 Fields have all been seeded and the rain has aided germination! Parking lot completed. Site visit with developer. order goals and implement Grass improvement plan in November.  

Warrenton Branch Greenway Extension Warrenton

Bid- November 2019-January 2019 Comm/Dev has reviewed the plans and submitted comments for the designer to respond to.  Working on options to provide educational signage in lieu of wetland credits.   
MM Pierce Elementary School Connector Trail Remington Construction 7/2019- 10/2019 Project completed! Ribbon Cutting held Schools are utilizing the trail for education and health and wellness initiatives.  
Woods @Warrenton Trail Warrenton Construction-  Pre-construction meeting to be held on 11/4/19.  Determine Construction schedule  

Last updated 10-31-2019