Project Status

Print
Press Enter to show all options, press Tab go to next option

Project

Start/End Dates

Status

Next Phase

View/Map

Central Fauquier Sports Complex, Warrenton
Construction 3/4/19- 8/2020
Trees are being staked and planted; two rectangular fields need to be graded with topsoil then sprigged. Outfield/backstop fencing is being installed. Artificial turf plans approved work will start when field dries out. Main trail continues to have asphalt applied when temps are high enough!  Sod/sprig the remaining fields. Continue planting trees/shrubs. Put protective covering over the outfield fencing. Erosion and sediment control improvements.

Central Fauquier Sports Complex Utility Plan Warrenton

  Septic drain field permameter tests completed Design septic field based upon tests   
Rappahannock Station Civil War Battlefield Remington
Design 3/27/2019- 10/2019 
  Site plan was submitted to Community Development before Christmas. 75% plans submitted also.
Respond to design comments from Comm/Dev when issued.  
Comprehensive Plan Update November 2019-2020 Kickoff meeting was held on 12/13/19. SWOT analysis in process and information gathering. January 8th is the next meeting to discuss programming, maintenance and facilities.  

Riverside Preserve Canoe and Kayak Launch Marshall

Design  VA Outdoor Foundation creating public easement documents based upon master plan for park Take easement to BOS for approval; include kayak/canoe launch and trail bridge in capital Improvement Program so staff can apply for grants.  
Northern Fauquier County Pool  Marshall Feasibility Study 2/8/2017-7/2019 Marshall Community Advisory Board has chosen the Marshall community center site for a pool.  We will begin working on a design scope for the pool at the next Advisory meeting on 1/27/20.  
Southern Fauquier Sports Complex  Remington Concept-  Concept plan completed  Level of service needs for the number of fields will be determined during Comp Plan Update.   
Mintbrook Proffer 4 rectangular fields Bealton Construction- 2018- October 2019 Fields have been fertilized. Site visit with developer. order goals. Install ADA parking spots  

Warrenton Branch Greenway Extension Warrenton

Bid- November 2019-January 2020 Electrical conduit design has been completed and reviewed by staff with comments. Finalize design and bid out in January 2020.  
Woods @Warrenton Trail Warrenton Construction-  Groundscapes was given a Notice to proceed to gather permits needed to start construction. To be completed by 1/19/20. Determine Construction schedule and issue Notice To Proceed for construction.  

Last updated 1-3-2020