Show/Hide

Coronavirus updates are available on the Emergency Event Information Page.

Project Status

Print
Press Enter to show all options, press Tab go to next option

Project

Start/End Dates

Status

Next Phase

View/Map

Central Fauquier Sports Complex, Warrenton
Construction 3/4/19- 8/2020
The artificial turf field has been installed. The roads and parking lots have received their top coats of asphalt. Trash cans, benches, road signs and bleachers have been installed. GMAX testing for artificial turf for safety. Mark lines in parking lots for parking and installing car stops. Complete work on Meetze Rd turn lanes.

Central Fauquier Sports Complex Utility Plan Warrenton

Postponed to FY23  Dominion Power has designed the electrical paths based upon load letters. Septic plans are in review with Dept. of Health.  
Rappahannock Station Civil War Battlefield Remington

Design: May 2020

Construction: FY23

  100% plans submitted for review.Easement holders are reviewing the plans
Work with American Battlefield Trust on transfer of property and DHR for easements. Over the summer.  
Comprehensive Plan Update November 2019- September 2020 Phase 2 which is public input and Stakeholder feedback is almost complete. Compile all data collected by citizen input and develop a draft of the final report with level of service data and recommendations for capital projects, maintenance and programming.  

Riverside Preserve Canoe and Kayak Launch Marshall

Design  VA Outdoor Foundation Easement is going to the BOS for approval on July 9th. An MOU with DGIF to build the kayak/canoe launch is going the same day. Work on funding to build the kayak/canoe launch.  
Northern Fauquier County Pool  Marshall Scope of Work Marshall Community Advisory Board has chosen the Marshall community center site for a pool.  Sub committee will be set up to develop scope of work, when meetings return.  
Southern Fauquier Sports Complex  Remington Concept-  Concept plan completed  Level of service needs for the number of fields will be determined during Comp Plan Update.   
Mintbrook Proffer 4 rectangular fields Bealton Opening August 2020  Mowing  Looking to add topdressing to the grass to speed up growth and fill in bare areas.  

Warrenton Branch Greenway Extension Warrenton

Bid opening July 21st IFB was issued on June 25,2020. Pre bid meeting is 7/7/20. Open bids on 7/21/20 and evaluate them for completeness and accuracy.  
Woods @Warrenton Trail Warrenton Construction- 1/28/20- 5/28/20 Trail sections outside the wetland are having topsoil and grass removed and a stone based installed.  Sleeper deck boardwalk was approved and will be installed in the wetlands. Pave sections that will be asphalt.  

Last updated 7-6-2020